Back to projects

Purchase of a service vehicle

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$21,180
Federal share50%

of $42.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
2018
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Nov 28, 2017(actual)
Construction end
Sep 30, 2018(actual)

Also in Laval