Replacement of the S1 hydraulic jack at the Francis-Hughes Avenue garage

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$19,000
Federal share50%

of $38.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
2017
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 14, 2016(actual)
Construction end
Nov 28, 2016(actual)