Transit Shop Equipment Upgrade / Replacement
Federal contribution
$783,850
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2019
2018201920202021
Built
Approved 20 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jul 17, 2019(actual)
- Construction end
- Jun 2, 2021(actual)
Against the original forecast
- Construction start10 months lateforecast Sep 10, 2018
- Construction end5 months lateforecast Dec 31, 2020
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51243 in the federal list. How to read these figures.