Rapid Overhead Doors at Washrack
Federal contribution
$184,310
Federal share37%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2019
201820192020
Built
Approved 20 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jul 1, 2019(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Aug 19, 2019
- Construction end4 weeks lateforecast Mar 6, 2020
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51245 in the federal list. How to read these figures.