Installation of bus information panels at stops
Federal contribution
$16,693
Federal share50%
of $33.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2017
201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Trois-Rivières (STTR)
- Construction start
- Oct 17, 2017(actual)
- Construction end
- Sep 30, 2020(actual)
Also in Trois-Rivières