Back to projects

Tools/equipment

Trois-Rivières, Quebec

completePublic TransitPTIF
Federal contribution
$19,863
Federal share50%

of $39.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
20182019
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 3, 2018(actual)
Construction end
May 1, 2019(actual)

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51259 in the federal list. How to read these figures.