Pedestrian and Cycling Bridges: Chief Peguis Trail

Winnipeg, Manitoba

completeActive TransportationPTIF
Federal contribution
$3.1M
$3,075,954
Federal share46%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Winnipeg
Construction start
Apr 16, 2018(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 2, 2018
  • Construction end7 months earlyforecast Oct 31, 2020

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51265 in the federal list. How to read these figures.