Analysis of potential for reserved lanes and preferential measures
Federal contribution
$12,481
Federal share50%
of $25.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2017
201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Société de transport de Trois-Rivières (STTR)
- Construction start
- Feb 1, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51268 in the federal list. How to read these figures.