Back to projects

Two city buses in 2018

Trois-Rivières, Quebec

completePublic TransitPTIF
Federal contribution
$880,247
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 7, 2018
2018
Built

Approved 8 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 1, 2017(actual)
Construction end
Aug 31, 2018(actual)

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51272 in the federal list. How to read these figures.