Protected Bike Lanes: McDermot Avenue/Bannatyne Avenue (Phase 2)

Winnipeg, Manitoba

completeActive TransportationPTIF
Federal contribution
$1.5M
$1,532,346
Federal share44%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Winnipeg
Construction start
Jun 11, 2018(actual)
Construction end
Sep 14, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 22, 2018
  • Construction end7 weeks earlyforecast Nov 2, 2018