Protected Bike Lanes: McDermot Avenue/Bannatyne Avenue (Phase 2)
Federal contribution
$1.5M
$1,532,346
Federal share44%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jun 11, 2018(actual)
- Construction end
- Sep 14, 2018(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 22, 2018
- Construction end7 weeks earlyforecast Nov 2, 2018
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51296 in the federal list. How to read these figures.