Campbell Highway Bitiminous Surface Treatment
Federal contribution
$641,250
Federal share75%
of $855.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2017
20182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- May 24, 2017(actual)
- Construction end
- Jul 31, 2019(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Sep 1, 2019
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51314 in the federal list. How to read these figures.