Campbell Highway Reconstruction (km 73-79)

Watson Lake, Yukon

completeHighways and RoadsSCF
Federal contribution
$3.5M
$3,463,551
Federal share75%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
20182019
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
Jul 31, 2017(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2017