Campbell Highway Reconstruction (km 73-79)
Federal contribution
$3.5M
$3,463,551
Federal share75%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2017
20182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Jul 31, 2017(actual)
- Construction end
- Jul 31, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2017
Also in Watson Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51316 in the federal list. How to read these figures.