Raw Water Source Location
Lac Seul First Nation, Ontario
Federal contribution
$25,000
Federal share50%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Lac Seul First Nation
- Construction start
- Mar 28, 2018(actual)
- Construction end
- Sep 23, 2019(actual)
Against the original forecast
- Construction start14 months lateforecast Jan 16, 2017
- Construction end3 months lateforecast Jun 30, 2019
Also in Lac Seul First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51355 in the federal list. How to read these figures.