Distribution System Upgrade

Lac Seul First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$21,250
Federal share43%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
20182019
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Lac Seul First Nation
Construction start
Mar 28, 2018(actual)
Construction end
Sep 23, 2019(actual)

Against the original forecast

  • Construction start14 months lateforecast Jan 16, 2017
  • Construction end6 months lateforecast Mar 31, 2019