Stopping compressor oil from entering the air system that runs through the plant to control the solenoids and valves during operation of the water treatment facility

Seine River First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$2,151
Federal share50%

of $4.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Seine River First Nation
Construction start
May 30, 2019(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start2.2 years lateforecast Apr 1, 2017
  • Construction end2 months lateforecast Oct 30, 2019

Also in Seine River First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51376 in the federal list. How to read these figures.