Stopping compressor oil from entering the air system that runs through the plant to control the solenoids and valves during operation of the water treatment facility
Seine River First Nation, Ontario
Federal contribution
$2,151
Federal share50%
of $4.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Seine River First Nation
- Construction start
- May 30, 2019(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start2.2 years lateforecast Apr 1, 2017
- Construction end2 months lateforecast Oct 30, 2019
Also in Seine River First Nation
- Seine River Community Centre Renovations$3.0M
- Seine River Water Treatment Distribution System Rehabilitation$1.5M
- Repairing the Control Panel in Water Treatment Facility that controls all functions related to running solenoids, dosing pumps, and backwash capabilities that were once present$25.0K
- Valve Replacement$20.0K
- Replacing or adding to the Filter Media inside the filter media tanks that provides filtration of particles present in the inflowing water from the treatment cycle after flocculation.$7.0K