Filter and Pump System Repairs at Water Treatment Plant
Sheguiandah First Nation, Ontario
Federal contribution
$36,656
Federal share50%
of $73.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Sheguiandah
- Construction start
- May 8, 2018(actual)
- Construction end
- Apr 15, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2017
- Construction end12 months lateforecast Mar 31, 2018