Culvert replacement
Sheguiandah First Nation, Ontario
Federal contribution
$2,510
Federal share50%
of $5.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Sheguiandah
- Construction start
- May 17, 2017(actual)
- Construction end
- Aug 24, 2017(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 1, 2017
- Construction end7 months earlyforecast Mar 31, 2018
Also in Sheguiandah First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51395 in the federal list. How to read these figures.