Culvert replacement

Sheguiandah First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$2,510
Federal share50%

of $5.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Sheguiandah
Construction start
May 17, 2017(actual)
Construction end
Aug 24, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2018

Also in Sheguiandah First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51395 in the federal list. How to read these figures.