Rehabilitation and Securing of 42 Well Heads throughout the Community
Curve Lake First Nation, Ontario
Federal contribution
$72,775
Federal share46%
of $159.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Curve Lake First Nation
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Feb 28, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 30, 2017
- Construction end8 weeks earlyforecast Apr 25, 2018