Recalibration of the Curve Lake Pump House

Curve Lake First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$4,509
Federal share25%

of $18.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Curve Lake First Nation
Construction start
Sep 29, 2017(actual)
Construction end
Mar 8, 2018(actual)

Against the original forecast

  • Construction start9 months lateforecast Jan 1, 2017
  • Construction end11 months lateforecast Mar 30, 2017