Recalibration of the Curve Lake Pump House
Curve Lake First Nation, Ontario
Federal contribution
$4,509
Federal share25%
of $18.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Curve Lake First Nation
- Construction start
- Sep 29, 2017(actual)
- Construction end
- Mar 8, 2018(actual)
Against the original forecast
- Construction start9 months lateforecast Jan 1, 2017
- Construction end11 months lateforecast Mar 30, 2017