Back to projects

Storm Sewer Improvement and Reconstruction of Lower Portion of John Street

Sundridge, Ontario

completeWastewaterCWWF
Federal contribution
$89,794
Federal share36%

of $249.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 30, 2017(actual)
Construction end
Jun 8, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017
  • Construction end3 months lateforecast Mar 1, 2018

Also in Sundridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51429 in the federal list. How to read these figures.