Storm Sewer Improvement and Reconstruction of Lower Portion of John Street
Federal contribution
$89,794
Federal share36%
of $249.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Village of Sundridge
- Construction start
- Oct 30, 2017(actual)
- Construction end
- Jun 8, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2017
- Construction end3 months lateforecast Mar 1, 2018
Also in Sundridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51429 in the federal list. How to read these figures.