Back to projects

Supervisory Control And Data Acquisition system Installation at the Cornwall Island Water Treatment Plant

Mohawks of Akwesasne First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$78,796
Federal share39%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018201920202021
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Mohawks of Akwesasne
Construction start
Apr 30, 2018(actual)
Construction end
Sep 20, 2021(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 1, 2017
  • Construction end3 months lateforecast Jun 30, 2021

Also in Mohawks of Akwesasne First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51453 in the federal list. How to read these figures.