Inspect/repair Cornwall Island water treatment plant vertical turbine pumps
Mohawks of Akwesasne First Nation, Ontario
Federal contribution
$45,030
Federal share30%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018201920202021
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Mohawks of Akwesasne
- Construction start
- Nov 1, 2019(actual)
- Construction end
- Sep 20, 2021(actual)
Against the original forecast
- Construction start2.6 years lateforecast Apr 1, 2017
- Construction end3 months lateforecast Jun 30, 2021
Also in Mohawks of Akwesasne First Nation
- Replacement of granular activated carbon filter at the St. Regis Wastewater Treatment Plant$149.0K
- Supervisory Control And Data Acquisition system Installation at the Cornwall Island Water Treatment Plant$78.8K
- Supervisory Control And Data Acquisition System Installation at the St. Regis Wastewater Treatment Plant$66.8K
- Replace submersible wastewater pumps at the St. Regis Wastewater Treatment Plant$30.1K
- Replace damaged submersible pump with submersible shredder pump$10.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51456 in the federal list. How to read these figures.