Design and Contract Administration for Community Flooding Control - Installation of new Stormwater Pipe

Fort William First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$47,500
Federal share50%

of $95.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Fort William First Nation
Construction start
Sep 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start7 months lateforecast Feb 1, 2017
  • Construction end3 months lateforecast Jan 1, 2020

Also in Fort William First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51530 in the federal list. How to read these figures.