Design and Contract Administration Extension of Water Distribution and Fire Protection Improvements

Fort William First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$19,500
Federal share50%

of $39.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Fort William First Nation
Construction start
Mar 1, 2018(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start13 months lateforecast Feb 1, 2017
  • Construction end2.8 years lateforecast Jun 1, 2017