Stormwater Pond Rehabilitation
Federal contribution
$1.5M
$1,470,350
Federal share46%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of Brampton
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 2, 2017
- Construction end5 weeks lateforecast Feb 28, 2020
Also in Brampton
- Transit Maintenance & Storage Facility$69.9M
- Protecting our future: Flood mitigation and physical, economic, social and cultural resilience for historic downtown Brampton, on by reconstructing 600M of the concrete Etobicoke Creek bypass channel$38.9M
- 2023 Replacement Buses$25.5M
- 2020-2024 Bus Refurbishments$22.2M
- 2020 Growth Buses$18.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51552 in the federal list. How to read these figures.