Cole's Road Water, Sewer and Road Upgrading
Victoria, Newfoundland and Labrador
Federal contribution
$66,351
Federal share32%
of $204.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Victoria
- Construction start
- May 24, 2018(actual)
- Construction end
- Aug 26, 2020(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 1, 2018
- Construction end2 months earlyforecast Oct 31, 2020
Also in Victoria
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51593 in the federal list. How to read these figures.