Ash's Lane Water and Sewer Extension and Drainage Improvements
Victoria, Newfoundland and Labrador
Federal contribution
$93,212
Federal share40%
of $233.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 23, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Victoria
- Construction start
- Jul 21, 2021(actual)
- Construction end
- Aug 25, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 10, 2021
- Construction end2 months earlyforecast Oct 30, 2021