Ash's Lane Water and Sewer Extension and Drainage Improvements

Victoria, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$93,212
Federal share40%

of $233.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 23, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Victoria
Construction start
Jul 21, 2021(actual)
Construction end
Aug 25, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 10, 2021
  • Construction end2 months earlyforecast Oct 30, 2021