Dean's Road Water, Wastewater and Road Upgrading

Victoria, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$145,772
Federal share40%

of $364.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Victoria
Construction start
Jun 22, 2020(actual)
Construction end
Oct 31, 2020(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2020
  • Construction end4 weeks earlyforecast Nov 30, 2020