Beothic Arena Chiller Replacement

Lumsden, Newfoundland and Labrador

completeRecreationSCF
Federal contribution
$39,173
Federal share33%

of $117.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Lumsden
Construction start
Oct 1, 2018(actual)
Construction end
Oct 9, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 15, 2018
  • Construction end13 months earlyforecast Oct 31, 2020

Also in Lumsden