Schedule
Announced and approvedOct 14, 2020
20212022
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Lumsden
- Construction start
- Sep 5, 2022(actual)
- Construction end
- Sep 30, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2022
- Construction end4 weeks lateforecast Sep 1, 2022
Also in Lumsden
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56771 in the federal list. How to read these figures.