Back to projects

Water Main Intake Replacement

Lumsden, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$301,108
Federal share40%

of $752.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
202220232024
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Lumsden
Construction start
Nov 1, 2023(actual)
Construction end
Sep 20, 2024(actual)

Against the original forecast

  • Construction start6 months earlyforecast May 8, 2024
  • Construction end3 months lateforecast Jun 30, 2024

Also in Lumsden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62228 in the federal list. How to read these figures.