Portage Regional Recreation Authority - Splash Island (# 2)
Federal contribution
$78,162
Federal share33%
of $234.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Portage La Prairie
- Construction start
- Sep 6, 2017(actual)
- Construction end
- Jun 14, 2018(actual)
Against the original forecast
- Construction end2 weeks lateforecast May 31, 2018
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51609 in the federal list. How to read these figures.