Portage Regional Recreation Authority - Splash Island (# 2)

Portage la Prairie, Manitoba

completeRecreationSCF
Federal contribution
$78,162
Federal share33%

of $234.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
2018
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 6, 2017(actual)
Construction end
Jun 14, 2018(actual)

Against the original forecast

  • Construction end2 weeks lateforecast May 31, 2018

Also in Portage la Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51609 in the federal list. How to read these figures.