Manitoba Ave. Pathway (#5)

Selkirk, Manitoba

completeActive TransportationSCF
Federal contribution
$158,333
Federal share33%

of $475.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Selkirk
Construction start
May 1, 2018(actual)
Construction end
Dec 4, 2019(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Oct 31, 2019