Lift Station Upgrading/Replacement and Sewer Main Cleaning - Low Road and Point Road
Cartwright, Newfoundland and Labrador
Federal contribution
$162,268
Federal share29%
of $568.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Burin
- Construction start
- Nov 11, 2018(actual)
- Construction end
- Aug 15, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 6, 2018
- Construction end5 months lateforecast Mar 31, 2020