Back to projects

New Sewer System - Main Road South

Cartwright, Newfoundland and Labrador

completeWastewaterRNIS
Federal contribution
$549,558
Federal share38%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Cartwright
Construction start
Sep 26, 2020(actual)
Construction end
Aug 2, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 30, 2020
  • Construction end6 months lateforecast Jan 30, 2021

Also in Cartwright

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53867 in the federal list. How to read these figures.