New Sewer System - Main Road South
Cartwright, Newfoundland and Labrador
Federal contribution
$549,558
Federal share38%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Cartwright
- Construction start
- Sep 26, 2020(actual)
- Construction end
- Aug 2, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 30, 2020
- Construction end6 months lateforecast Jan 30, 2021
Also in Cartwright
- Trans Labrador Highway - Route 510 - Widening and Hard Surfacing of Phase III - 160 km east of Happy Valley-Goose Bay to Cartwright Junction (126 km)$29.0M
- Water System Improvements$555.9K
- Sanitary Sewer$504.9K
- Replacement Sewer System-Low Road$269.6K
- Lift Station Upgrading/Replacement and Sewer Main Cleaning - Low Road and Point Road$162.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53867 in the federal list. How to read these figures.