Water System Improvements
Cartwright, Newfoundland and Labrador
Federal contribution
$555,870
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Cartwright
- Construction start
- Aug 10, 2023(actual)
- Construction end
- Oct 2, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2023
- Construction end4 months lateforecast Jun 15, 2024
Also in Cartwright
- Trans Labrador Highway - Route 510 - Widening and Hard Surfacing of Phase III - 160 km east of Happy Valley-Goose Bay to Cartwright Junction (126 km)$29.0M
- New Sewer System - Main Road South$549.6K
- Sanitary Sewer$504.9K
- Replacement Sewer System-Low Road$269.6K
- Lift Station Upgrading/Replacement and Sewer Main Cleaning - Low Road and Point Road$162.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61034 in the federal list. How to read these figures.