Sweetapple Drive and Tower Road- Road Upgrading

Mount Moriah, Newfoundland and Labrador

completeHighways and RoadsSCF
Federal contribution
$51,501
Federal share20%

of $262.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Mount Moriah
Construction start
Sep 18, 2018(actual)
Construction end
Oct 30, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 9, 2018
  • Construction end2 years earlyforecast Oct 31, 2020