Back to projects

Water and Sewer - City Boundary to Serpentine Road

Mount Moriah, Newfoundland and Labrador

approvedDrinking WaterGIS
Federal contribution
$805,043
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2020
today
202120222023202420252026
BuiltForecast

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Mount Moriah
Construction start
May 11, 2026(forecast)
Construction end
Aug 28, 2026(forecast)

Also in Mount Moriah

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56891 in the federal list. How to read these figures.