Water and Sewer Replacement Along Route 450 and Serpentine Road

Mount Moriah, Newfoundland and Labrador

underwayWastewaterGIS
Federal contribution
$838,355
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023202420252026
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
Town of Mount Moriah
Construction start
Oct 7, 2024(actual)
Construction end
Oct 31, 2025(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 29, 2024

Also in Mount Moriah

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61095 in the federal list. How to read these figures.