Additional Artesian Wells
St. Mary's, Newfoundland and Labrador
Federal contribution
$77,888
Federal share32%
of $243.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
2018201920202021
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of St. Mary's
- Construction start
- Aug 29, 2018(actual)
- Construction end
- Apr 9, 2021(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 15, 2018
- Construction end3 weeks earlyforecast Apr 30, 2021