Replacement of Water Tank - St. Mary's

St. Mary's, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$333,246
Federal share40%

of $833.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 14, 2021
202120222023
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Mary's
Construction start
Jul 1, 2022(actual)
Construction end
Jul 19, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2022