Replacement of Water Tank - St. Mary's
St. Mary's, Newfoundland and Labrador
Federal contribution
$333,246
Federal share40%
of $833.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 14, 2021
202120222023
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Mary's
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Jul 19, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2022
Also in St. Mary's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56787 in the federal list. How to read these figures.