Replacement of culverts throughout St. Mary's

St. Mary's, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$49,635
Federal share40%

of $124.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Mary's
Construction start
Jun 26, 2024(actual)
Construction end
Sep 16, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 31, 2024
  • Construction end6 weeks earlyforecast Oct 31, 2024

Also in St. Mary's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67345 in the federal list. How to read these figures.