Veterans Community Hall Upgrades

Swan River, Manitoba

completeRecreationSCF
Federal contribution
$16,666
Federal share33%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
20182019
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Swan River
Construction start
Jan 7, 2019(actual)
Construction end
May 5, 2019(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Mar 30, 2019