Pump House Extension

Daniel's Harbour, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$108,194
Federal share33%

of $324.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Daniel's Harbour
Construction start
Sep 24, 2018(actual)
Construction end
May 2, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 20, 2018
  • Construction end8 months earlyforecast Dec 19, 2019