Pump House Extension
Daniel's Harbour, Newfoundland and Labrador
Federal contribution
$108,194
Federal share33%
of $324.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Daniel's Harbour
- Construction start
- Sep 24, 2018(actual)
- Construction end
- May 2, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 20, 2018
- Construction end8 months earlyforecast Dec 19, 2019
Also in Daniel's Harbour