Back to projects

Road Upgrades - Clinic and Humbers

Daniel's Harbour, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$99,098
Federal share33%

of $297.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Daniel's Harbour
Construction start
Aug 25, 2020(actual)
Construction end
Sep 17, 2020(actual)

Against the original forecast

  • Construction start9 months earlyforecast Jun 1, 2021
  • Construction end10 months earlyforecast Jul 31, 2021