Road Upgrading - Circular Road and Depot Road
Daniel's Harbour, Newfoundland and Labrador
Federal contribution
$37,792
Federal share24%
of $158.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
20242025
Built
Approved 11 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Daniel's Harbour
- Construction start
- Jul 15, 2025(actual)
- Construction end
- Aug 9, 2025(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 3, 2025
- Construction end8 weeks lateforecast Jun 17, 2025
Also in Daniel's Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67361 in the federal list. How to read these figures.