Bill Thorpe Walking Bridge - Refurbishment

Fredericton, New Brunswick

completeRecreationSCF
Federal contribution
$1.3M
$1,304,993
Federal share33%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 27, 2017
2018201920202021
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Fredericton
Construction start
Apr 26, 2021(actual)
Construction end
Jul 16, 2021(actual)

Against the original forecast

  • Construction start19 months lateforecast Sep 23, 2019
  • Construction end18 months lateforecast Dec 31, 2019