Road Rehabilitation
Federal contribution
$181,227
Federal share33%
of $543.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2018
2018
Built
Approved 10 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Sep 10, 2017(actual)
- Construction end
- Jun 22, 2018(actual)
Against the original forecast
- Construction end3 months earlyforecast Oct 1, 2018
Also in Saint John