Watermain Renewal
Federal contribution
$501,797
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Lac du Bonnet
- Construction start
- Jun 10, 2019(actual)
- Construction end
- Aug 6, 2019(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2019
- Construction end8 weeks earlyforecast Sep 30, 2019
Also in Lac du Bonnet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51750 in the federal list. How to read these figures.