Back to projects

Rural Water Pipeline

Lac du Bonnet, Manitoba

completeDrinking WaterCWWF
Federal contribution
$539,074
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
20192020
Built

Approved 11 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Mar 20, 2019(actual)
Construction end
Jun 22, 2020(actual)

Against the original forecast

  • Construction end4 months earlyforecast Oct 31, 2020

Also in Lac du Bonnet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52153 in the federal list. How to read these figures.